Subject :- Modernisation of Kurnool-Cuddapah canal-Environmental clearance regarding.
1. Irrigation and C.A.D. department, govt. of Andhra Pradesh may refer to their letter No.SE/ICC/KNL/TS/AEE3/CWC/824 dated 30.1.96 and subsequent letter dated 30.0.97 on the subject.
2. The Ministry of Environment and Forests has carefully considered your application. It is noted that the proposal envisages (i) construction of a new barrage at Sunkesula in place of the dilapidated existing anicut and repair of other anicuts. (ii) Construction of alaganur balancing reservoir. The entire length of the KC main canal and all the distributaries will be lined. Existing old and dilapidated canal related structures such as bridges, aqueducts, cross drainage works, off takes, measuring devices etc. will be reconstructed or repaired.
3. The Ministry of Environment and Forests hereby accords environmental clearance as per the provision of Environmental Impact Assessment notification, 1994, subject to the strict labourers employed during the construction of the project to avoid destruction of vegetation cover in the surrounding areas. For this, fuel depots may be opened at the site and adequate provision made in the budget to cover the cost.
4. Officials from Regional Office Ministry of Environment and Forests. Government of India, Bangalore who would be monitoring the implementation of Environmental safeguards should be given full cooperation, facilities and documents/data by project proponents during their inspection.
5. The responsibility of implementation of environmental safeguards rests fully with the Government of Andhra Pradesh.
6. In case of change in the scope of the project, project would require a fresh appraisal.
7. The Ministry reserve the right to add additional safeguard measures subsequently if found, necessary and to take action including revoking of the clearance under the provisions of the environmental (Protection) Act, 1986, to ensure effective implementation of the suggested safeguard measures in time bound and satisfactory manner.
8. This clearance letter is valid for a period of five years from the date of issue of this letter for construction of barrage, balancing reservoir and other related works.
Additional Director/Joint Director
To
(Dr. S. Bhowmik)
Additional Director
Chief Engineer (Projects)
Irrigation and CAD Department
Govt. of Andhra Pradesh
T.G.P. Complex Mamillapalli (V)
Cuddapah, Andhra Pradesh.
Copy to:
1. Secretary (Irrigation) govt. of Andhra Pradesh, Secretariat, Hyderabad-500022.
2. Adviser (I&CAD), Planning Commission, Yojana Bhawan, New Delhi.
3. The chairman, Central Water Commission, Sewa Bhawan, R.K. Puram, New Delhi -110 066.
4. Regional Office, Ministry of environment & Forests, Bangalore.
5. Shri. Harjit Singh, Sr. Adviser, MOE&F.
6. Guard file.
Additional Director/Joint Director
Model Letters According Env. Clearance
Impact Assessment Division Home Page