ANNEXURE
‘D’
FORMAT FOR PROJECT PREPARATION
1.
Name of the FDA, JFMC/ EDC and their
detailed composition.
2.
Location of the project
-
Name of the State, District, Forest Division with head quarters, Block and Villages.
-
Map of the project area (s).
- Extent and description of the
watershed including their standard identification number as per National
Watershed Atlas of India.
- Extent of forestland, community land,
panchayat land etc.
- Total treatable area to be taken up
under the project.
3. General description
of the forest covered by the Territorial/ Wildlife Division
4. Extent and
Distribution of
- Dense,
open and scrub forest
- Composition
of forests
5. Socio-Economic Profile of the villages
to be included in the project area. (To be furnished for each project village.)
-
Total Population – SC/ST/OBC and
others.
-
Number of households.
-
Land holding and distribution.
-
Total Livestock population.
-
Number and category of livestock.
-
Total estimated fodder requirement and
its present availability indicating the source of supply.
- Total estimated fuelwood requirement
and its present availability indicating the source of supply.
-
Gap in supply and demand of fuelwood
and fodder.
-
Existence of JFMCs and activities
undertaken in the past in protection and development of forests.
6. Degree of
pressure on forest resources:
-
Fuelwood
-
Fodder
-
Grazing
-
Small Timber
-
NTFP
-
Others
7.
Interventions Required:
-
Aided Natural Regeneration.
-
Artificial Regeneration.
-
Pasture Development.
-
Coastal shelterbelt Plantations.
-
Bamboo
-
-
Mixed plantation of trees having MFP
and Medicinal values.
-
Regeneration of perennial herbs and
shrubs of Medicinal values.
8. Work Schedule as per the micro plan
showing phasing and costing of Individual Activities (give physical and
financial figures for each intervention, year-wise, for the project duration.
9. The approved prevailing wage rates in
the project area (s)/ District. (Copy of the relevant order to be enclosed)
10. Mutual obligations, responsibilities
which villages are willing to undertake and indicators of success.
7.
Sharing of usufructs as per the
provisions made in the JFM Rsolution of the State.
8.
9.
Monitoring, Evaluation and Reporting
Schedule.
10.
Fund
flow mechanism. Undertaking to the effect that the procedure laid down by the
NAREB, MoEF in this regard shall be followed by the Chairperson and the Member
Secretary of the FDA.
***********