GANGA ACTION PLAN PHASE-II (Main Stem) * |
||
|
|
|
|
|
|
|
(Rupees in
Crores) |
|
YEAR OF LAUNCH |
: |
July 1995/Oct. 1996 (For W.B.) |
|
SCHEDULE OF COMPLETION |
: |
March 1999/Dec. 2001
(For W.B.) |
|
COST SANCTIONED
(till 12/09) |
: |
Rs. 446.02 |
|
FUND RELEASED
(till 12/09) |
: |
Rs. 437.52 |
|
FUND UTILISED
(till 9/09) (Including State Share) |
: |
Rs. 302.61 |
|
FINANCIAL PROGRESS
(%) |
: |
67.85% |
|
NO. OF SCHEMES
SANCTIONED |
: |
157 |
|
NO. OF SCHEMES
COMPLETED |
: |
109 |
|
STATES COVERED |
: |
4 |
|
TOWNS COVERED |
: |
30 |
|
RIVERS COVERED |
: |
2 |
|
STP CAPACITY SANCTIONED |
: |
279.61
mld |
|
STP CAPACITY CREATED |
: |
137.34 mld |
|
*à Includes Mahananda River |
|
|
_files/image002.gif)