GANGA ACTION PLAN PHASE-II (Supreme Court Towns) |
||
|
|
|
|
|
|
|
(Rupees in
Crores) |
|
YEAR OF LAUNCH |
: |
October 1996 |
|
SCHEDULE OF COMPLETION |
: |
February 1999 |
|
COST SANCTIONED
(till 12/09) |
: |
Rs. 189.64 |
|
FUND RELEASED
(till 12/09) |
: |
Clubbed
with Main Stem |
|
FUND UTILISED
(till 9/09) (Including State
Share) |
: |
Rs. 101.79 |
|
FINANCIAL PROGRESS
(%) |
: |
53.68% |
|
NO. OF SCHEMES
SANCTIONED |
: |
166 |
|
NO. OF SCHEMES
COMPLETED |
: |
110 |
|
STATES COVERED |
: |
4 |
|
TOWNS COVERED |
: |
30 |
|
RIVERS COVERED |
: |
1 |