SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
YAMUNA ACTION PLAN |
|||||||||
|
CITY : AGRA |
|||||||||
|
1 |
Improved Wood Crematoria |
IWC |
16.11 |
01/07/1994 |
100 |
13.01 |
00.00 |
13.01 |
C |
|
2 |
Land Acquisition |
LA |
881.76 |
28/02/1997 |
100 |
699.70 |
00.00 |
699.70 |
C |
|
3 |
Low Cost Sanitation |
LCS |
205.70 |
07/08/2001 |
100 |
201.50 |
00.00 |
201.50 |
C |
|
4 |
I&D Trans Yamuna area |
I&D |
906.61 |
28/03/2001 |
100 |
908.93 |
00.00 |
908.93 |
C |
|
5 |
I&D Cis Yamuna area |
I&D |
1050.33 |
10/04/2001 |
100 |
1044.38 |
00.00 |
1044.38 |
C |
|
6 |
STP(Effluent Channel,Trans Yamuna area) |
STP |
74.08 |
07/08/2001 |
100 |
71.55 |
00.00 |
71.55 |
C |
|
7 |
Rehabilitation of MPS,RM and Eff.channel(Part-I) |
MPS |
896.78 |
04/10/1999 |
100 |
892.94 |
00.00 |
892.94 |
C |
|
8 |
Afforestation |
AFF |
02.71 |
22/09/1998 |
100 |
02.63 |
00.00 |
02.63 |
C |
|
9 |
I&D Bhuri-Nagla Nalla in Cis Yamuna Area |
I&D |
101.76 |
23/04/1999 |
100 |
85.47 |
00.00 |
85.47 |
C |
|
10 |
STP(Cis-Yamuna Area) |
STP |
2210.63 |
30/03/2001 |
100 |
2208.63 |
00.00 |
2208.63 |
C |
|
11 |
I&D Anurag Nagar Nala in Cis-Yamuna Area |
I&D |
201.05 |
29/04/1999 |
100 |
198.19 |
00.00 |
198.19 |
C |
|
12 |
Rehabilitation of MPS,RM and Eff.Channel(Part-II) |
MPS |
495.08 |
20/02/2001 |
100 |
489.32 |
00.00 |
489.32 |
C |
|
13 |
I&D works of ISPAT Udyog Nala(Trans Yamuna Area) |
I&D |
69.27 |
07/02/2001 |
100 |
68.25 |
00.00 |
68.25 |
C |
|
14 |
Land Acquisition(2.25 mld STP, Oxidation Pond) |
LA |
78.64 |
24/12/1998 |
100 |
60.83 |
00.00 |
60.83 |
C |
|
15 |
Sewage Treatment Plant(Cis Yamuna Area, 2.25 mld) |
STP |
47.71 |
11/01/1999 |
100 |
47.42 |
00.00 |
47.42 |
C |
|
16 |
River Front Development |
RFD |
07.25 |
11/12/1998 |
100 |
02.66 |
00.00 |
02.66 |
C |
|
17 |
Municipal Reforms |
OTH |
271.71 |
04/12/2002 |
0 |
00.00 |
00.00 |
00.00 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
7517.18 |
6995.41 |
00.00 |
6995.41 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |
SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
EXTENDED YAMUNA ACTION PLAN |
|||||||||
|
CITY : AGRA |
|||||||||
|
1 |
Laborators Equipment for Fecal Ciliform Testing |
01.50 |
26/06/2001 |
100 |
01.50 |
00.00 |
01.50 |
C |
|
|
2 |
Fire Fighting System (for 78 mld, CIS Yamuna Area) |
37.17 |
27/06/2001 |
100 |
35.57 |
00.00 |
35.57 |
C |
|
|
3 |
Power Connection (78 mld CIS Yamuna Area) |
16.20 |
04/07/2001 |
100 |
15.21 |
00.00 |
15.21 |
C |
|
|
4 |
Addl. work of Rehabilitation of MPS,RM (CIS) |
63.75 |
04/07/2001 |
100 |
61.03 |
00.00 |
61.03 |
C |
|
|
5 |
Low Cost Sanitation |
235.55 |
05/07/2001 |
100 |
201.60 |
00.00 |
201.60 |
C |
|
|
6 |
Tapping of Krishna Colony Drains (CIS Yamuna) |
02.17 |
09/07/2001 |
100 |
01.29 |
00.00 |
01.29 |
C |
|
|
7 |
Approach Road and Bridge at waterworks (IPS) |
09.39 |
09/07/2001 |
100 |
09.33 |
00.00 |
09.33 |
C |
|
|
8 |
Protection Works(Khoza & Peepal) |
22.68 |
09/07/2001 |
100 |
22.68 |
00.00 |
22.68 |
C |
|
|
9 |
Remodelling of Tapping (Mantola Nala |
35.25 |
09/07/2001 |
100 |
35.72 |
00.00 |
35.72 |
C |
|
|
10 |
Remodelling of Strand Road Sewer |
34.28 |
09/07/2001 |
100 |
34.66 |
00.00 |
34.66 |
C |
|
|
11 |
Public Participation |
PP |
15.00 |
13/07/2001 |
100 |
11.30 |
00.00 |
11.30 |
C |
|
12 |
Low Cost Sanitation |
LCS |
14.99 |
06/08/2001 |
100 |
11.43 |
00.00 |
11.43 |
C |
|
13 |
Lining works (10 and 2.25 mld) |
LCS |
128.80 |
07/09/2001 |
100 |
128.78 |
00.00 |
128.78 |
C |
|
14 |
Remodeling of Sewage Channel(78 mld STP) |
LCS |
25.76 |
04/02/2002 |
100 |
25.63 |
00.00 |
25.63 |
C |
|
15 |
Replacement of existing Rising Main (900 mm dia) |
LCS |
185.85 |
04/02/2002 |
100 |
96.62 |
00.00 |
96.62 |
C |
|
16 |
Additional Works (Cis-Yamuna Area) |
LCS |
83.98 |
04/02/2002 |
100 |
83.95 |
00.00 |
83.95 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
912.32 |
776.30 |
00.00 |
776.30 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |
SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
YAMUNA ACTION PLAN-II |
|||||||||
|
CITY : AGRA |
|||||||||
|
1 |
Sewage Treatment Plant,WB and PS |
STP |
810.15 |
10/02/2006 |
76 |
499.48 |
00.00 |
499.48 |
O |
|
2 |
STP & IND works |
STP |
8438.54 |
27/03/2006 |
30 |
3573.05 |
641.45 |
4214.50 |
O |
|
3 |
Public Participation & Awareness for 8 towns |
PP |
895.64 |
29/03/2007 |
90 |
488.69 |
138.94 |
627.63 |
O |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
10144.33 |
4561.22 |
780.39 |
5341.61 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |