SANCTION/PROGRESS OF SCHEMES UNDER NRCP
[Rupees in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
OTHER RIVER CONSERVATION PLAN |
|||||||||
|
CITY : AHMEDABAD |
|||||||||
|
1 |
I&D (Disilting of Sewer) |
I&D |
100.91 |
06/07/2000 |
100 |
93.83 |
00.00 |
93.83 |
C |
|
2 |
I&D (WTS Zone V Part-I) |
I&D |
167.58 |
23/06/2000 |
100 |
184.62 |
00.00 |
184.62 |
C |
|
3 |
I&D ETS Zone-IV Pt-I(Incl.of sewer cleaning eqpt.) |
I&D |
640.02 |
27/06/2000 |
100 |
630.44 |
00.00 |
630.44 |
C |
|
4 |
Land Acquisition for STP |
LA |
225.82 |
29/11/1996 |
100 |
225.82 |
00.00 |
225.82 |
C |
|
5 |
Relief Sewer Zone-2,3 |
I&D |
69.77 |
30/06/2000 |
100 |
73.40 |
00.00 |
73.40 |
C |
|
6 |
Electric Crematoria |
EC |
57.46 |
29/06/2000 |
100 |
52.97 |
00.00 |
52.97 |
C |
|
7 |
Rising Main |
EC |
228.34 |
22/06/2000 |
100 |
287.16 |
00.00 |
287.16 |
C |
|
8 |
Renovation of 7 Sewage Pumping Station |
MPS |
401.11 |
29/06/2000 |
100 |
203.98 |
00.00 |
203.98 |
C |
|
9 |
Renovation of 3 Sewage Pumping Station |
MPS |
310.76 |
30/06/2000 |
100 |
244.23 |
00.00 |
244.23 |
C |
|
10 |
Western Trunk Sewer Zone-5 Part-II |
I&D |
1290.83 |
27/06/2000 |
100 |
1482.39 |
00.00 |
1482.39 |
C |
|
11 |
Low Cost Sanitation |
LCS |
106.03 |
30/06/2000 |
100 |
73.48 |
00.00 |
73.48 |
C |
|
12 |
STP at Pirana (mld 106) |
STP |
3121.92 |
12/02/2001 |
100 |
2808.46 |
00.00 |
2808.46 |
C |
|
13 |
STP at Vasna (mld 126) |
STP |
3475.32 |
14/02/2001 |
100 |
3147.64 |
00.00 |
3147.64 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
10195.87 |
9508.42 |
00.00 |
9508.42 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO
REVISED COST AND REVISED DATE |
|
|
* --> REFERS TO
SCHEMES NOT YET APPROVED |
|
|
C -->
COMPLETED, O--> ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER
FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS-->
INTERMEDIATE PUMPING STATION, IWC--> IMPROVED
WOOD CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF
LCS |