SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                                [Rupees in Lakhs]

 

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











OTHER RIVER CONSERVATION PLAN

CITY : BHADRACHALAM

1

Main Pumping Station

MPS

24.50

11/02/2002

0

00.00

00.00

00.00

O

2

Sewage Treatment Plant

STP

27.50

11/02/2002

100

54.77

00.00

54.77

C

3

Land Acquisition

LA

03.10

26/11/1997

100

02.06

00.00

02.06

C

4

Low Cost Sanitation

LCS

28.53

30/06/1997

100

14.26

00.00

14.26

C

5

River Front Development

RFD

21.30

27/12/1995

100

22.88

00.00

22.88

C

6

Interception & Diversion

I&D

95.77

27/05/1998

85

115.70

00.00

115.70

O











TOTAL

200.70

209.67

00.00

209.67











# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS