SANCTION/PROGRESS OF SCHEMES UNDER NRCP
[Rupees
in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
OTHER RIVER CONSERVATION PLAN |
|||||||||
|
CITY : BHADRACHALAM |
|||||||||
|
1 |
Main Pumping Station |
MPS |
24.50 |
11/02/2002 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
2 |
Sewage Treatment Plant |
STP |
27.50 |
11/02/2002 |
100 |
54.77 |
00.00 |
54.77 |
C |
|
3 |
Land Acquisition |
LA |
03.10 |
26/11/1997 |
100 |
02.06 |
00.00 |
02.06 |
C |
|
4 |
Low Cost Sanitation |
LCS |
28.53 |
30/06/1997 |
100 |
14.26 |
00.00 |
14.26 |
C |
|
5 |
River Front Development |
RFD |
21.30 |
27/12/1995 |
100 |
22.88 |
00.00 |
22.88 |
C |
|
6 |
Interception & Diversion |
I&D |
95.77 |
27/05/1998 |
85 |
115.70 |
00.00 |
115.70 |
O |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
200.70 |
209.67 |
00.00 |
209.67 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO
REVISED COST AND REVISED DATE |
|
|
* --> REFERS TO
SCHEMES NOT YET APPROVED |
|
|
C -->
COMPLETED, O--> ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER
FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS-->
INTERMEDIATE PUMPING STATION, IWC--> IMPROVED
WOOD CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF
LCS |