SANCTION/PROGRESS OF
SCHEMES UNDER NRCP
[Rupees
in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
OTHER
RIVER CONSERVATION PLAN |
|||||||||
|
CITY : CHITRAKUT |
|||||||||
|
1 |
Interception & Diversion |
I&D |
372.46 |
24/04/2009 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
2 |
Sewage Treatment Plant (4.7 mld) |
STP |
139.56 |
24/04/2009 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
3 |
Low Cost Sanitation |
LCS |
62.85 |
24/04/2009 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
4 |
River Front Development |
RFD |
03.10 |
24/04/2009 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
5 |
Improved Wood Crematoria |
IWC |
06.84 |
24/04/2009 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
6 |
Public Awareness & Participation |
PP |
11.60 |
24/04/2009 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
7 |
Land Acquisition |
LA |
24.00 |
24/04/2009 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
620.42 |
00.00 |
00.00 |
00.00 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |