SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
YAMUNA ACTION PLAN |
|||||||||
|
CITY : DELHI |
|||||||||
|
1 |
EC at Sarai Kale Khan |
EC |
414.07 |
13/12/2001 |
100 |
270.33 |
00.00 |
270.33 |
C |
|
2 |
STP-Sen nursing home(10 mld) |
STP |
607.39 |
06/01/2001 |
100 |
618.06 |
00.00 |
618.06 |
C |
|
3 |
STP-Delhi Gate Nala (10 mld) |
STP |
737.01 |
06/01/2001 |
100 |
733.25 |
00.00 |
733.25 |
C |
|
4 |
Laying of Wazirabad Road Trunk Sewer |
I&D |
9234.00 |
19/11/2008 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
5 |
STP(54.6 mld new & Rehabiliation (91 and 182 mld) |
STP |
16985.00 |
19/11/2008 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
27977.47 |
1621.64 |
00.00 |
1621.64 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |
SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
EXTENDED YAMUNA ACTION PLAN |
|||||||||
|
CITY : DELHI |
|||||||||
|
1 |
Electric Crematoria |
EC |
178.43 |
14/03/2002 |
100 |
178.43 |
00.00 |
178.43 |
C |
|
2 |
Sewage Treatment Plant (3 mld FAB Technolgy) |
EC |
178.28 |
01/11/2001 |
100 |
149.54 |
00.00 |
149.54 |
C |
|
3 |
Sewage Treatment Plant ( 3 mld SAFF Technolgy) |
EC |
185.90 |
01/11/2001 |
100 |
139.55 |
00.00 |
139.55 |
C |
|
4 |
Sewage Treatment Plant (2 mld SAFF Technology) |
EC |
147.14 |
01/11/2001 |
100 |
146.40 |
00.00 |
146.40 |
C |
|
5 |
Sewage Treatment Plan (2 mld, FAB Technology) |
EC |
147.35 |
01/11/2001 |
100 |
127.36 |
00.00 |
127.36 |
C |
|
6 |
Low Cost Sanitation (1146 nos.) |
LCS |
14920.00 |
03/02/2003 |
100 |
13179.70 |
00.00 |
13179.70 |
C |
|
7 |
Public Participation |
PP |
215.55 |
10/08/2001 |
100 |
125.94 |
00.00 |
125.94 |
C |
|
8 |
2 mld disnfection plant at Sen Nursing Home |
PP |
48.33 |
19/03/2002 |
100 |
114.60 |
00.00 |
114.60 |
C |
|
9 |
Sewer Cleaning Machines |
LCS |
284.64 |
03/08/2001 |
100 |
286.38 |
00.00 |
286.38 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
16305.62 |
14447.90 |
00.00 |
14447.90 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |
SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
YAMUNA ACTION PLAN-II |
|||||||||
|
CITY : DELHI |
|||||||||
|
1 |
Public Relation Components |
PP |
720.36 |
26/03/2008 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
2 |
Public Participation & Awareness |
PP |
630.43 |
27/03/2008 |
0 |
515.97 |
00.00 |
515.97 |
O |
|
3 |
Appointment(Consultant)for preparation MP and DPRs |
OTH |
96.73 |
07/07/2008 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
4 |
Consltant (preparation of MP,DPRs & F.Study) |
OTH |
162.25 |
07/07/2008 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
5 |
Consultant(preparation for MP,DPRs and F.Study) |
OTH |
76.15 |
07/08/2008 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
6 |
I&D (Laying of Bela Road Trunk Sewer) |
I&D |
3666.00 |
05/01/2009 |
19 |
495.00 |
153.00 |
648.00 |
O |
|
7 |
Appointment of Consultant (IS & Capacity Builing) |
OTH |
94.13 |
25/02/2009 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
8 |
Laying of Wazirabad Road Trunk Sewer |
I&D |
9234.00 |
19/11/2008 |
30 |
2096.00 |
198.00 |
2294.00 |
O |
|
9 |
STP(New 54 mld and Rehabilitation of 91.2 & 182.4) |
STP |
16985.00 |
19/11/2008 |
20 |
2186.00 |
504.00 |
2690.00 |
O |
|
10 |
Rehabilitation work of Ring Road Trunk Sewer |
I&D |
8767.00 |
19/01/2007 |
20 |
1610.00 |
404.00 |
2014.00 |
O |
|
11 |
Sewage Treatment Plant (135 mld) |
STP |
6503.40 |
19/01/2007 |
36 |
2510.00 |
423.00 |
2933.00 |
O |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
46935.45 |
9412.97 |
1682.00 |
11094.97 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT DEVELOPMENT,
STP--> SEWAGE TREATMENT PLANT, P-S-->
PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |