SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                    [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











YAMUNA ACTION PLAN

CITY : ETAWAH

1

Land Acquisition

LA

100.00

13/05/1994

100

52.00

00.00

52.00

C

2

Low Cost Sanitation

LCS

72.99

07/08/2001

100

70.32

00.00

70.32

C

3

Improved Wood Crematoria

IWC

10.45

16/12/2002

100

10.44

00.00

10.44

C

4

Interception & Diversion

I&D

66.99

13/02/2002

100

65.18

00.00

65.18

C

5

STP & Effluent Channel

STP

241.67

18/10/1995

100

375.22

00.00

375.22

C

6

Afforestation

AFF

03.90

02/12/1998

100

02.91

00.00

02.91

C

7

Public Participation

PP

10.80

11/11/1999

100

10.13

00.00

10.13

C

8

River Front Development

RFD

28.67

21/12/1998

100

11.16

00.00

11.16

C











TOTAL

535.47

597.36

00.00

597.36











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS

 


  

SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                       [Rupees in Lakhs]











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











EXTENDED YAMUNA ACTION PLAN

CITY : ETAWAH

1

Lining Works of STP

LCS

14.29

06/08/2001

100

12.13

00.00

12.13

C

2

Public Participatipn

PP

10.00

100

09.99

00.00

09.99

C











TOTAL

24.29

22.12

00.00

22.12











 

 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS