SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                    [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











YAMUNA ACTION PLAN

CITY : FARIDABAD

1

MPS Zone -I(20 mld)

MPS

253.64

23/12/1996

100

238.11

00.00

238.11

C

2

MPS Zone -II(45 mld)

MPS

319.55

23/12/1996

100

300.41

00.00

300.41

C

3

MPS -Zone -III(50 mld)

MPS

629.33

26/12/1996

100

586.47

00.00

586.47

C

4

IPS Zone -III A

MPS

331.34

24/12/1996

100

304.41

00.00

304.41

C

5

Land Acquisition for STP-I

LA

16.78

13/12/1996

100

160.73

00.00

160.73

C

6

Land Acquisition for STP-II

LA

71.50

13/12/1996

100

71.50

00.00

71.50

C

7

Land Acquisition for STP-III

LA

137.50

13/12/1996

100

195.32

00.00

195.32

C

8

I&D Zone-III A

I&D

454.70

08/01/1999

100

376.32

00.00

376.32

C

9

Sewage Treatment Plant-I(20 mld)

STP

655.22

13/12/1996

100

641.78

00.00

641.78

C

10

Sewage Treatment Plant-II(45 mld)

STP

1481.97

13/12/1996

100

1463.83

00.00

1463.83

C

11

STP-III (50 mld)

STP

1568.18

13/12/1996

100

1523.21

00.00

1523.21

C

12

Improved Wood Crematoria

IWC

04.39

27/11/1998

100

04.39

00.00

04.39

C

13

I&D Zone-II

I&D

224.43

14/08/1998

100

220.62

00.00

220.62

C

14

I&D Zone-III B

I&D

314.21

14/01/1999

100

257.82

00.00

257.82

C

15

I&D Zone-I

I&D

223.15

01/05/2000

100

194.88

00.00

194.88

C

16

Low Cost Sanitation

LCS

81.33

27/11/1998

100

75.37

00.00

75.37

C

17

Public Participation

PP

10.80

08/12/1999

100

00.00

00.00

00.00

C











TOTAL

6778.02

6615.17

00.00

6615.17











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS

 


   SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                    [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











EXTENDED YAMUNA ACTION PLAN

CITY : FARIDABAD

1

Additional Sludge Drying Beds (20 mld)

PP

54.62

03/07/2001

100

50.95

00.00

50.95

C

2

Laboratory Equipment (all 6 towns)

PP

09.00

03/07/2001

100

08.72

00.00

08.72

C

3

Public Participation ( all 6 towns)

PP

77.00

16/07/2001

100

75.59

00.00

75.59

C

4

Pilot Plant at 20 mld STP Zone-I

PP

103.95

10/09/2001

100

104.04

00.00

104.04

C

5

Low Cost Sanitation(23 Nos.)

LCS

274.81

05/07/2001

100

271.32

00.00

271.32

C

6

Interception & Diversion

I&D

276.17

22/01/2001

100

273.45

00.00

273.45

C











TOTAL

795.55

784.07

00.00

784.07











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS


 

SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                       [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











YAMUNA ACTION PLAN-II

CITY : FARIDABAD

1

DPR Preparation for Sewerage works in eight towns

OTH

1081.87

21/11/2006

82

849.85

65.94

915.79

O

2

Sewer lines (Phase-II/Stage-II)

I&D

833.36

07/11/2007

96

764.82

131.21

896.03

O

3

Public Participation & Awareness for 6 towns

PP

410.44

29/03/2007

95

270.00

34.86

304.86

O

4

Additional Sewerage Works

I&D

83.90

12/03/2007

100

59.70

05.40

65.10

C

5

Consultancy for Preparation of Reform Action Plan

OTH

149.43

19/09/2006

100

149.07

00.00

149.07

C

6

Consultancy for Engineering Technology

OTH

202.39

19/09/2006

100

202.95

00.00

202.95

C

7

Common ReformsImplementation programmes

OTH

1182.00

07/07/2009

55

161.78

331.82

493.60

O

8

Public Participation and Awareness

PP

71.66

28/03/2008

85

17.51

09.73

27.24

O











TOTAL

4015.05

2475.68

578.96

3054.64











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS