|
SANCTION/PROGRESS OF SCHEMES UNDER NRCP
[Rupees
in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
OTHER RIVER CONSERVATION PLAN |
|||||||||
|
CITY : GANGTOK |
|||||||||
|
1 |
Sewerage and Sewage Treatment Plant |
STP |
1717.00 |
17/01/2008 |
50 |
1466.87 |
00.00 |
1466.87 |
O |
|
2 |
STP and Rehabilitation of Sewer Main (Bye Pass) |
STP |
799.20 |
11/08/2009 |
0 |
00.00 |
00.00 |
00.00 |
O |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
2516.20 |
1466.87 |
00.00 |
1466.87 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO
REVISED COST AND REVISED DATE |
|
|
* --> REFERS TO
SCHEMES NOT YET APPROVED |
|
|
C -->
COMPLETED, O--> ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER
FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS-->
INTERMEDIATE PUMPING STATION, IWC--> IMPROVED
WOOD CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF
LCS |