SANCTION/PROGRESS OF SCHEMES UNDER NRCP
[Rupees in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
GAP II(SUPREME COURT TOWNS) |
|||||||||
|
CITY : GARULIA |
|||||||||
|
1 |
Sewage Treatment Plant |
STP |
46.90 |
06/09/2005 |
100 |
46.00 |
00.00 |
46.00 |
C |
|
2 |
Afforeststion |
AFF |
05.22 |
27/08/2004 |
100 |
03.21 |
00.00 |
03.21 |
C |
|
3 |
Public Participation & Awareness Programme |
PP |
07.68 |
16/03/2004 |
100 |
05.91 |
00.00 |
05.91 |
C |
|
4 |
River Front Development |
RFD |
13.59 |
10/06/2002 |
100 |
13.63 |
00.00 |
13.63 |
C |
|
5 |
Interception & Diversion |
I&D |
87.17 |
28/01/2000 |
100 |
86.85 |
00.00 |
86.85 |
C |
|
6 |
Lifting Station (I&D) |
I&D |
69.50 |
04/12/2001 |
100 |
60.83 |
00.00 |
60.83 |
C |
|
7 |
Main Pumping Station |
MPS |
148.77 |
04/12/2001 |
100 |
139.88 |
00.00 |
139.88 |
C |
|
8 |
Sewage Treatment Plant (7.9 mld) |
STP |
91.90 |
04/12/2001 |
100 |
88.69 |
00.00 |
88.69 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
470.73 |
445.00 |
00.00 |
445.00 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF I&D,
CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |