SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
YAMUNA ACTION PLAN |
|||||||||
|
CITY : GHAZIABAD |
|||||||||
|
1 |
Improved Wood Crematoria |
IWC |
13.74 |
23/06/2000 |
100 |
13.10 |
00.00 |
13.10 |
C |
|
2 |
Low Cost Sanitation |
LCS |
40.96 |
07/02/2001 |
100 |
40.68 |
00.00 |
40.68 |
C |
|
3 |
I&D (Part-I) in Trans-Hindon |
I&D |
145.80 |
15/07/1999 |
100 |
146.08 |
00.00 |
146.08 |
C |
|
4 |
I&D(Part-II) in Trans-Hindon |
I&D |
266.24 |
20/07/1999 |
100 |
266.87 |
00.00 |
266.87 |
C |
|
5 |
Land Acquisition |
LA |
1160.75 |
28/02/1997 |
100 |
1160.71 |
00.00 |
1160.71 |
C |
|
6 |
I&D(Part-III) in Trans-Hindon |
I&D |
471.68 |
16/03/1995 |
100 |
468.41 |
00.00 |
468.41 |
C |
|
7 |
I&D(Part-IV) in Trans-Hindon |
I&D |
518.94 |
17/01/2000 |
100 |
519.93 |
00.00 |
519.93 |
C |
|
8 |
I&D(Part-I) Cis-Hindon |
I&D |
367.22 |
13/10/2000 |
100 |
357.38 |
00.00 |
357.38 |
C |
|
9 |
I&D(Part-II) Cis-Hindon |
I&D |
872.72 |
24/12/1999 |
100 |
872.65 |
00.00 |
872.65 |
C |
|
10 |
Main Pumping Station THA & Rising Main |
MPS |
734.34 |
19/01/2000 |
100 |
735.45 |
00.00 |
735.45 |
C |
|
11 |
Main Pumping Station |
MPS |
711.55 |
07/01/2000 |
100 |
666.24 |
00.00 |
666.24 |
C |
|
12 |
Afforestation |
AFF |
02.19 |
08/12/1998 |
100 |
02.19 |
00.00 |
02.19 |
C |
|
13 |
STP(Cis-Hindon Area,70 mld) |
STP |
1778.50 |
09/11/2000 |
100 |
1764.56 |
00.00 |
1764.56 |
C |
|
14 |
STP(Trans Hindon Area,56 mld) |
STP |
1511.88 |
23/11/2000 |
100 |
1506.59 |
00.00 |
1506.59 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
8596.51 |
8520.84 |
00.00 |
8520.84 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |
SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
EXTENDED YAMUNA ACTION PLAN |
|||||||||
|
CITY : GHAZIABAD |
|||||||||
|
1 |
Intelligent Project Management |
OTH |
10.37 |
27/02/2003 |
100 |
00.00 |
00.00 |
00.00 |
C |
|
2 |
Interception and Diversion |
I&D |
269.32 |
29/10/2002 |
100 |
251.14 |
00.00 |
251.14 |
C |
|
3 |
Miscellaneous |
I&D |
20.48 |
10/09/2001 |
100 |
20.48 |
00.00 |
20.48 |
C |
|
4 |
Networking (15 towns) |
OTH |
38.25 |
27/07/2001 |
100 |
38.25 |
00.00 |
38.25 |
C |
|
5 |
Public Participation |
PP |
11.40 |
13/07/2001 |
100 |
11.38 |
00.00 |
11.38 |
C |
|
6 |
Laboratory Equip. at Ghaziabad,Saharanpur & Noida |
PP |
07.50 |
06/07/2001 |
100 |
07.40 |
00.00 |
07.40 |
C |
|
7 |
Remedial Measures for Non-Seweage Facilities |
PP |
00.64 |
06/07/2001 |
100 |
00.55 |
00.00 |
00.55 |
C |
|
8 |
Miscellaneous |
PP |
43.02 |
07/09/2001 |
100 |
43.01 |
00.00 |
43.01 |
C |
|
9 |
I&D Zone-IV (CHA Part-I) |
I&D |
139.32 |
04/07/2001 |
100 |
124.87 |
00.00 |
124.87 |
C |
|
10 |
Fire Fighting System (70 mld) |
I&D |
31.67 |
27/06/2001 |
100 |
31.67 |
00.00 |
31.67 |
C |
|
11 |
Low Cost Sanitation |
LCS |
252.29 |
27/06/2001 |
100 |
211.10 |
00.00 |
211.10 |
C |
|
12 |
fire Protection Works (56 mld, THA Area) |
LCS |
37.18 |
28/06/2001 |
100 |
34.80 |
00.00 |
34.80 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
861.44 |
774.65 |
00.00 |
774.65 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |
SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
YAMUNA ACTION PLAN-II |
|||||||||
|
CITY : GHAZIABAD |
|||||||||
|
1 |
Reform Action Plan for 8 towns |
OTH |
170.03 |
24/11/2006 |
100 |
169.08 |
00.00 |
169.08 |
C |
|
2 |
Consultancy Services for Master Plan |
OTH |
1193.58 |
29/11/2006 |
95 |
972.71 |
53.00 |
1025.71 |
O |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
1363.61 |
1141.79 |
53.00 |
1194.79 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |