SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                    [Rupees in Lakhs]

 

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











GAP II(SUPREME COURT TOWNS)

CITY : GOPESHWAR

1

River Front Development

RFD

01.05

18/12/1998

100

00.95

00.00

00.95

C

2

Low Cost Sanitation

LCS

14.31

18/12/1998

100

14.31

00.00

14.31

C

3

Interception & Diversion

I&D

15.00

25/01/2005

100

15.00

00.00

15.00

C











TOTAL

30.36

30.26

00.00

30.26











 

 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS