SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                    [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











YAMUNA ACTION PLAN

CITY : GURGAON

1

Public Participation

PP

10.80

08/12/1999

100

00.00

00.00

00.00

C

2

Land Acquisition for STP

LA

207.91

12/05/1996

100

212.14

00.00

212.14

C

3

Afforestation

AFF

01.83

12/08/1998

100

01.43

00.00

01.43

C

4

Main Pumping Station

MPS

358.40

26/12/1996

100

339.99

00.00

339.99

C

5

Interception & Diversion

I&D

185.95

11/08/1998

100

170.11

00.00

170.11

C

6

STP Zone-I(30 mld)

STP

1076.53

12/05/1996

100

1055.17

00.00

1055.17

C

7

Improved Wood Crematoria

IWC

04.46

28/09/1998

100

04.26

00.00

04.26

C

8

Low Cost Sanitation(units of 10 Seats)

LCS

39.11

14/01/1999

100

33.10

00.00

33.10

C











TOTAL

1884.99

1816.20

00.00

1816.20











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS

 

 

 

 

   SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                    [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











EXTENDED YAMUNA ACTION PLAN

CITY : GURGAON

1

Low Cost Sanitation

LCS

64.14

03/07/2001

100

57.85

00.00

57.85

C

2

Additional Sludge Beds(30 mld)

LCS

15.10

03/07/2001

100

15.03

00.00

15.03

C

3

I&D of Sewer along Palam Court Road Old DLF

I&D

99.57

03/07/2001

100

98.66

00.00

98.66

C

4

Interception & Diversion

I&D

265.00

05/07/2001

100

264.29

00.00

264.29

C

5

I&D Zone-C

I&D

133.91

05/09/2001

100

131.61

00.00

131.61

C

6

I&D Zone-D

I&D

246.39

05/09/2001

100

239.71

00.00

239.71

C

7

I&D Zone-E

I&D

36.75

07/09/2001

100

36.05

00.00

36.05

C

8

Improved Wood Crematoria

IWC

18.79

27/04/2002

100

00.00

00.00

00.00

C











TOTAL

879.65

843.20

00.00

843.20











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS

 


   SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                    [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











YAMUNA ACTION PLAN-II

CITY : GURGAON

1

Sewer Line(Phase-II/Stage-II)

I&D

632.48

07/09/2007

44

138.27

125.80

264.07

O











TOTAL

632.48

138.27

125.80

264.07











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS