SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                           [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











OTHER RIVER CONSERVATION PLAN

CITY : INDORE

1

Interception & Diversion

I&D

139.43

26/03/1999

100

131.81

00.00

131.81

C

2

Main Pumping Station

MPS

432.82

01/03/2001

100

432.82

00.00

432.82

C

3

Interception & Diversion Part-II

I&D

253.42

03/11/2000

100

253.00

00.00

253.00

C

4

Sewage Treatment Plant

STP

2780.46

06/06/2002

100

2499.12

00.00

2499.12

C

5

Land Acquisition

LA

115.00

23/05/1996

100

113.36

00.00

113.36

C

6

Crematoria(EC)

EC

83.59

03/12/1999

100

54.84

00.00

54.84

C

7

Low Cost Sanitation

LCS

206.03

06/12/1999

100

206.03

00.00

206.03

C

8

River Front Development

RFD

08.46

13/09/1999

100

06.00

00.00

06.00

C











TOTAL

4019.21

3696.98

00.00

3696.98











 

 

 

       

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS