SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                                [Rupees in Lakhs]

 

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











OTHER RIVER CONSERVATION PLAN

CITY : KAPURTHALA

1

Interception & Diversion

I&D

340.20

04/07/2001

100

275.87

00.00

275.87

C

2

STP(Including effluent channel)

STP

662.58

04/07/2001

100

775.09

09.96

785.05

C

3

Public Participation

PP

02.70

04/07/2001

100

03.32

00.00

03.32

C

4

Afforestation

AFF

03.78

04/07/2001

100

00.44

00.00

00.44

C

5

Land Acquisition

LA

247.00

04/07/2001

100

202.32

00.01

202.33

C











TOTAL

1256.26

1257.04

09.97

1267.01











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS