SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                             [Rupees in Lakhs]

 

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











OTHER RIVER CONSERVATION PLAN

CITY : KUMBAKONAM

1

Interception & Diversion

I&D

3189.33

26/03/2008

100

4025.95

00.05

4026.00

C

2

Interception & Diversion (Phase-I)

I&D

264.08

20/12/2001

100

247.94

00.02

247.96

C

3

Sewage Treatment Plant (17 mld)

STP

664.04

10/07/2008

65

441.04

12.89

453.93

O

4

River Front Development

RFD

14.87

16/09/2003

0

00.00

00.00

00.00

O

5

Bathing Ghat(10 Nos.)

RFD

27.30

16/09/2003

0

05.96

00.00

05.96

O

6

Dhobikhana (1 Nos)

RFD

12.96

16/09/2003

0

00.00

00.00

00.00

O

7

Solid Waste Management

SWM

164.16

16/09/2003

0

127.20

00.00

127.20

O

8

Low Cost Sanitation

LCS

73.71

16/09/2003

0

36.39

00.00

36.39

O











TOTAL

4410.45

4884.48

12.96

4897.44











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS