SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                               [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











OTHER RIVER CONSERVATION PLAN

CITY : MANCHARIAL

1

Sewage Treatment Plant

STP

34.18

14/11/2000

100

34.18

00.00

34.18

C

2

Sewage Treatment Plant

STP

26.65

14/11/2000

100

28.72

00.00

28.72

C

3

Interception and Diversion

I&D

124.61

24/12/1999

100

124.91

00.00

124.91

C

4

Low Cost Sanitation

LCS

28.36

30/06/1997

100

19.06

00.00

19.06

C

5

River Front Development

RFD

17.50

23/11/1995

100

17.19

00.00

17.19

C











TOTAL

231.30

224.06

00.00

224.06











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS