SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                                  [Rupees in Lakhs]

 

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











GANGA ACTION PLAN - II(MAIN STEM)

CITY : MIRZAPUR

1

Sewage Treatment Plant(Vindh.)

STP

76.97

10/06/2003

100

76.97

00.00

76.97

C

2

Interception and Diversion

I&D

134.80

14/07/2000

100

134.80

00.00

134.80

C

3

Storm Water Drainage at Vindhyachal

OTH

12.98

04/09/1996

100

07.59

00.00

07.59

C

4

Low Cost Sanitation

LCS

36.94

20/12/1999

100

31.43

00.00

31.43

C











TOTAL

261.69

250.79

00.00

250.79











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS