SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                    [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











YAMUNA ACTION PLAN

CITY : MUZAFFARNAGAR

1

Public Participation

PP

10.80

02/09/1999

100

10.42

00.00

10.42

C

2

Sewage Treatment Plant

STP

201.79

07/08/2001

100

198.57

00.00

198.57

C

3

I&D-II(Western Zone)

I&D

258.32

07/08/2001

100

258.05

00.00

258.05

C

4

Low Cost Sanitation

LCS

42.64

07/08/2001

100

42.50

00.00

42.50

C

5

Improved Wood Crematoria

IWC

02.11

09/08/1994

100

02.08

00.00

02.08

C

6

I&D(Part-I) Western Zone

I&D

304.76

30/03/2001

100

301.85

00.00

301.85

C

7

Land Acquisition

LA

359.00

28/02/1997

100

357.51

00.00

357.51

C











TOTAL

1179.42

1170.98

00.00

1170.98











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS

 


   SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                    [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











EXTENDED YAMUNA ACTION PLAN

CITY : MUZAFFARNAGAR

1

Miscellanous at STP

LCS

10.06

07/09/2001

100

09.78

00.00

09.78

C

2

Public Participation

PP

10.00

100

09.82

00.00

09.82

C

3

Low cost Sanitation

LCS

33.59

06/07/2001

100

17.96

00.00

17.96

C

4

I&D (Part-III)

I&D

52.87

06/07/2001

100

50.48

00.00

50.48

C











TOTAL

106.52

88.04

00.00

88.04











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS