SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
YAMUNA ACTION PLAN |
|||||||||
|
CITY : NOIDA |
|||||||||
|
1 |
Interception & Diversion(Part-II) |
I&D |
90.93 |
30/10/1996 |
100 |
89.37 |
00.00 |
89.37 |
C |
|
2 |
Improved Wood Crematoria |
IWC |
09.09 |
07/08/2001 |
100 |
09.11 |
00.00 |
09.11 |
C |
|
3 |
Low Cost Sanitation |
LCS |
40.50 |
15/06/1994 |
100 |
37.51 |
00.00 |
37.51 |
C |
|
4 |
Land Acquisition |
LA |
147.20 |
27/07/1994 |
100 |
147.22 |
00.00 |
147.22 |
C |
|
5 |
Interception & Diversion(Part-I) |
I&D |
428.61 |
30/03/2001 |
100 |
428.61 |
00.00 |
428.61 |
C |
|
6 |
UASB Sewage Treatment Plant(27 mld) |
STP |
796.89 |
20/02/2001 |
100 |
789.59 |
00.00 |
789.59 |
C |
|
7 |
UASB Sewage Treatment Plant(34 mld) |
STP |
1013.31 |
08/03/2001 |
100 |
1001.30 |
00.00 |
1001.30 |
C |
|
8 |
Renovation of Oxidation Ponds(9mld) |
STP |
35.44 |
28/07/1997 |
100 |
33.52 |
00.00 |
33.52 |
C |
|
9 |
Afforestation |
AFF |
04.55 |
06/05/1998 |
100 |
04.30 |
00.00 |
04.30 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
2566.52 |
2540.53 |
00.00 |
2540.53 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |
SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
EXTENDED YAMUNA ACTION PLAN |
|||||||||
|
CITY : NOIDA |
|||||||||
|
1 |
Fire Protection Works (34 mld) |
I&D |
32.39 |
26/06/2001 |
100 |
32.37 |
00.00 |
32.37 |
C |
|
2 |
Experimental Plant (2 mld for 27 mld UASB) |
I&D |
37.80 |
26/06/2001 |
100 |
27.57 |
00.00 |
27.57 |
C |
|
3 |
Fire Protection Works for 27 mld |
I&D |
33.25 |
26/06/2001 |
100 |
33.21 |
00.00 |
33.21 |
C |
|
4 |
Public Participation |
PP |
13.68 |
13/03/2001 |
100 |
13.68 |
00.00 |
13.68 |
C |
|
5 |
Barbed wire fencing (OP, Sector-54) |
PP |
21.05 |
10/09/2001 |
100 |
21.00 |
00.00 |
21.00 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
138.17 |
127.83 |
00.00 |
127.83 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |