SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
OTHER RIVER CONSERVATION PLAN |
|||||||||
|
CITY : RAMAGUNDAM |
|||||||||
|
1 |
Low Cost Sanitation |
LCS |
61.88 |
30/06/1997 |
100 |
58.39 |
00.00 |
58.39 |
C |
|
2 |
River Front Development |
RFD |
15.80 |
08/12/1995 |
100 |
16.57 |
00.00 |
16.57 |
C |
|
3 |
Sewage Treatment Plan (Zone-I) |
STP |
35.60 |
17/06/2002 |
100 |
16.06 |
00.00 |
16.06 |
C |
|
4 |
Interception & Diversion |
I&D |
262.17 |
27/01/2000 |
92 |
168.09 |
00.00 |
168.09 |
O |
|
5 |
Sewage Treatment Plant (WSP, 14 mld) |
STP |
79.00 |
03/02/2003 |
100 |
45.05 |
00.00 |
45.05 |
C |
|
6 |
Improved Wood Crematoria |
IWC |
01.30 |
02/07/2002 |
100 |
01.01 |
00.00 |
01.01 |
C |
|
7 |
Sewage Treatment Plant (Zone-II) |
STP |
118.80 |
17/06/2002 |
0 |
81.80 |
00.00 |
81.80 |
O |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
574.55 |
386.98 |
00.00 |
386.98 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |