SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
YAMUNA ACTION PLAN |
|||||||||
|
CITY : RADAUR |
|||||||||
|
1 |
Sewage Treatment Plant and Main Pumping Station |
STP |
49.86 |
18/10/2000 |
100 |
20.13 |
00.00 |
20.13 |
C |
|
2 |
Interception & Diversion |
I&D |
59.00 |
23/10/1997 |
100 |
48.84 |
00.00 |
48.84 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
108.86 |
68.97 |
00.00 |
68.97 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY WALL,
LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |