SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                                    [Rupees in Lakhs]

 

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











GAP II(SUPREME COURT TOWNS)

CITY : RANIPUR

 

1

Interception and Diversion in Zone-E-I

I&D

122.45

17/08/2001

100

109.09

00.00

109.09

C

2

Sewage Treatment Plant at Sarai Jamalpur

STP

31.28

17/08/2001

50

21.40

05.42

26.82

O

3

Renovation of Existing Out Fall Gravity Sewer

I&D

02.39

27/04/1998

100

02.26

00.00

02.26

C

4

Low Cost Sanitation

LCS

38.76

27/04/1998

100

36.48

00.00

36.48

C

5

Reorganisation of Seweage System of Zone-2(Jwalpur

I&D

197.67

24/06/2003

50

238.71

00.00

238.71

O











TOTAL

392.55

407.94

05.42

413.36











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS