SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                             [Rupees in Lakhs]

 

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











GAP II(SUPREME COURT TOWNS)

CITY : RUDRA PRAYAG

1

Public Participation & Awareness Programme

PP

04.50

25/08/2004

100

04.50

00.00

04.50

C

2

Interception & Diversion

I&D

54.58

17/05/2005

0

00.00

00.00

00.00

O

3

River Front Development(Bathing Ghat)

RFD

03.24

16/12/1998

100

03.15

00.00

03.15

C

4

Low Cost Sanitation

LCS

11.97

21/12/1998

100

11.97

00.00

11.97

C

5

Interception & Diversion

I&D

791.58

22/09/2009

0

00.00

00.00

00.00

O

6

Sewage Treatment Plant(3.0 mld)

STP

469.61

22/09/2009

0

00.00

00.00

00.00

O











TOTAL

1335.48

19.62

00.00

19.62











 

 

 

 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS