SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                    [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











YAMUNA ACTION PLAN

CITY : SAHARANPUR

1

I&D(Part-III)

I&D

182.04

07/08/2001

100

181.09

00.00

181.09

C

2

Public Participation

PP

10.80

11/11/1999

100

10.96

00.00

10.96

C

3

Sewage Treatment Plant(38 mld, UASB)

STP

1015.55

02/11/2000

100

1035.19

00.00

1035.19

C

4

I&D (Part-II)

I&D

173.99

07/06/1999

100

174.06

00.00

174.06

C

5

I&D C&G Part-I

I&D

243.49

07/08/2001

100

245.13

00.00

245.13

C

6

I&D C&G Part-II

I&D

258.27

28/10/1996

100

250.18

00.00

250.18

C

7

Low Cost Sanitation

LCS

29.89

13/01/1995

100

28.04

00.00

28.04

C

8

Improved Wood Crematoria

IWC

02.79

07/08/2001

100

02.79

00.00

02.79

C

9

Land Acquisition

LA

250.00

28/02/1997

100

171.92

00.00

171.92

C

10

I&D Part-III(Suplementary DPR)

I&D

29.07

13/09/1999

100

15.74

00.00

15.74

C











TOTAL

2195.89

2115.10

00.00

2115.10











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS

 


 

   SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                    [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











EXTENDED YAMUNA ACTION PLAN

CITY : SAHARANPUR

1

Remedial Measures for LCS

LCS

01.12

05/07/2001

100

01.06

00.00

01.06

C

2

Fire Fighting System (38 mld)

LCS

26.91

26/06/2001

100

26.31

00.00

26.31

C

3

Public Participation

PP

12.50

100

12.50

00.00

12.50

C

4

Fire Fighting System (I&D Rehabilitation Part-I)

PP

116.34

10/09/2002

100

111.25

00.00

111.25

C

5

Constrution of Addl. Slump for the MPS

I&D

56.36

27/06/2001

100

54.74

00.00

54.74

C

6

DG set at IPS Govindpur

I&D

12.70

06/08/2001

100

10.49

00.00

10.49

C

7

Low Cost Sanitation

LCS

64.80

07/09/2001

100

51.69

00.00

51.69

C











TOTAL

290.73

268.04

00.00

268.04











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS