SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                    [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











OTHER RIVER CONSERVATION PLAN

CITY : THANJAVUR

1

Solid Waste Management

OTH

365.35

14/11/2007

30

06.29

00.00

06.29

O

2

Interception & Diversion

I&D

253.70

20/05/2009

0

00.00

00.00

00.00

O

3

Interception & Diversion + Sewage Plant Treatment

I&D

5655.71

26/12/2001

100

6324.81

00.00

6324.81

C











TOTAL

6274.76

6331.10

00.00

6331.10











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS