SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                                    [Rupees in Lakhs]

 

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











GANGA ACTION PLAN - II(MAIN STEM)

CITY : TOLLY'S NALLAH

1

Interception & Diversion

I&D

1788.49

27/11/1998

81

1081.03

00.00

1081.03

O

2

Interception & Diversion

I&D

398.19

23/08/2001

82

344.36

00.00

344.36

O

3

Afforestation

AFF

03.35

26/08/2004

0

00.00

00.00

00.00

O

4

Public Participation & Awareness Programme

PP

11.34

25/08/2004

100

06.75

00.00

06.75

C

5

Lifting Station for Pollution Abatement

I&D

263.80

20/08/2009

0

00.00

00.00

00.00

O











TOTAL

2465.17

1432.14

00.00

1432.14











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS