SANCTION/PROGRESS OF SCHEMES UNDER NRCP
[Rupees
in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
GANGA ACTION PLAN - II(MAIN STEM) |
|||||||||
|
CITY : VARANASI |
|||||||||
|
1 |
Prevention of outflow of sewage |
I&D |
257.72 |
28/03/2001 |
100 |
249.49 |
06.09 |
255.58 |
C |
|
2 |
Interception & Diversion (ASSI-BHU) |
I&D |
1035.86 |
28/08/2001 |
49 |
734.80 |
174.98 |
909.78 |
O |
|
3 |
Interception & Diversion (Relieving Trunk Sewer) |
I&D |
2263.90 |
28/08/2001 |
74 |
1820.88 |
114.23 |
1935.11 |
O |
|
4 |
Sewage Treatment Plant at at Ramana (ASSI-BHU) |
STP |
603.73 |
12/09/2001 |
3 |
16.75 |
00.00 |
16.75 |
O |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
4161.21 |
2821.93 |
295.29 |
3117.22 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO
REVISED COST AND REVISED DATE |
|
|
* --> REFERS TO
SCHEMES NOT YET APPROVED |
|
|
C -->
COMPLETED, O--> ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER
FRONT DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS-->
INTERMEDIATE PUMPING STATION, IWC--> IMPROVED
WOOD CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF
LCS |