SANCTION/PROGRESS OF SCHEMES UNDER NRCP [Rupees in Lakhs]
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
OTHER RIVER CONSERVATION PLAN |
|||||||||
|
CITY : VIDISHA |
|||||||||
|
1 |
Low Cost Sanitation |
LCS |
35.75 |
30/12/1999 |
100 |
35.75 |
00.00 |
35.75 |
C |
|
2 |
Improved Wood Crematoria |
IWC |
04.32 |
13/10/1999 |
100 |
04.32 |
00.00 |
04.32 |
C |
|
3 |
River Front Development |
RFD |
26.74 |
13/10/1999 |
100 |
15.58 |
00.00 |
15.58 |
C |
|
4 |
Interception & Diversion |
I&D |
258.69 |
07/07/2005 |
100 |
242.99 |
00.00 |
242.99 |
C |
|
5 |
Sewage Treatment Plant |
STP |
107.77 |
23/04/2001 |
100 |
98.10 |
00.00 |
98.10 |
C |
|
6 |
Afforestation |
AFF |
03.25 |
03/07/1998 |
100 |
03.00 |
00.00 |
03.00 |
C |
|
7 |
Solid Waste Mangement |
SWM |
10.96 |
12/01/2000 |
100 |
09.27 |
00.00 |
09.27 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
447.48 |
409.01 |
00.00 |
409.01 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |