SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                    [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











OTHER RIVER CONSERVATION PLAN

CITY : VIDISHA

1

Low Cost Sanitation

LCS

35.75

30/12/1999

100

35.75

00.00

35.75

C

2

Improved Wood Crematoria

IWC

04.32

13/10/1999

100

04.32

00.00

04.32

C

3

River Front Development

RFD

26.74

13/10/1999

100

15.58

00.00

15.58

C

4

Interception & Diversion

I&D

258.69

07/07/2005

100

242.99

00.00

242.99

C

5

Sewage Treatment Plant

STP

107.77

23/04/2001

100

98.10

00.00

98.10

C

6

Afforestation

AFF

03.25

03/07/1998

100

03.00

00.00

03.00

C

7

Solid Waste Mangement

SWM

10.96

12/01/2000

100

09.27

00.00

09.27

C











TOTAL

447.48

409.01

00.00

409.01











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS