SANCTION/PROGRESS OF SCHEMES UNDER
NRCP
[Rupees
in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
OTHER RIVER CONSERVATION PLAN |
|||||||||
|
CITY : CUTTACK |
|||||||||
|
1 |
Interception & Diversion Part-II |
I&D |
119.90 |
17/06/2004 |
100 |
119.90 |
00.00 |
119.90 |
C |
|
2 |
Sewage Treatment Plant |
STP |
350.65 |
28/03/2001 |
100 |
350.65 |
00.00 |
350.65 |
C |
|
3 |
Interception & Diversion |
I&D |
320.27 |
28/03/2001 |
100 |
320.27 |
00.00 |
320.27 |
C |
|
4 |
Low Cost Sanitation |
LCS |
13.48 |
28/06/2000 |
100 |
13.48 |
00.00 |
13.48 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
804.30 |
804.30 |
00.00 |
804.30 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT DEVELOPMENT,
STP--> SEWAGE TREATMENT PLANT, P-S-->
PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |