SANCTION/PROGRESS OF SCHEMES UNDER NRCP
[Rupees
in Lakhs] |
|
|
|
|
|
|
|
|
|
|
|
|
S.NO. |
SCHEME NAME |
TYPE |
SANC.COST |
SANC.DATE |
%PHY PRG |
EXP.TILL |
EXP.DURING |
TOTAL EXP |
STATUS |
|
|
|
|
|
|
|
|
|
|
|
|
OTHER RIVER CONSERVATION PLAN |
|||||||||
|
CITY : JALLUNDHAR |
|||||||||
|
1 |
Sewage Treatment Plant |
STP |
2283.64 |
06/05/2002 |
100 |
2750.70 |
32.42 |
2783.12 |
C |
|
2 |
Main Pumping Station at Garha |
MPS |
878.76 |
06/08/2001 |
100 |
890.22 |
-11.46 |
878.76 |
C |
|
3 |
I&D (PART - I) |
I&D |
278.81 |
09/01/1996 |
100 |
278.70 |
00.00 |
278.70 |
C |
|
4 |
I&D (PART-IV) |
I&D |
240.36 |
01/03/1996 |
100 |
236.02 |
00.00 |
236.02 |
C |
|
5 |
I&D (PART-III) |
I&D |
193.10 |
10/01/1996 |
100 |
192.85 |
00.00 |
192.85 |
C |
|
6 |
I&D (Part-II) |
I&D |
258.10 |
15/01/1996 |
100 |
257.99 |
00.00 |
257.99 |
C |
|
7 |
I&D (Part-V) |
I&D |
274.82 |
25/01/1996 |
100 |
194.91 |
00.00 |
194.91 |
C |
|
8 |
I&D (Part-VII) |
I&D |
131.77 |
14/10/1996 |
73 |
221.31 |
00.00 |
221.31 |
O |
|
9 |
I&D (Part-VIII) |
I&D |
203.31 |
14/10/1996 |
94 |
263.97 |
82.00 |
345.97 |
O |
|
10 |
I&D (Part-VI) |
I&D |
236.30 |
10/01/1996 |
90 |
177.61 |
03.78 |
181.39 |
O |
|
11 |
Land Acquisition |
LA |
154.81 |
06/11/1995 |
100 |
2539.16 |
00.00 |
2539.16 |
C |
|
12 |
Improved Wood Crematoria |
IWC |
06.43 |
21/01/1997 |
100 |
06.02 |
00.00 |
06.02 |
C |
|
13 |
Low Cost Sanitation |
LCS |
68.87 |
17/01/1997 |
100 |
68.79 |
00.00 |
68.79 |
C |
|
14 |
Afforestation/Plantation |
AFF |
01.90 |
07/06/1998 |
45 |
01.06 |
00.00 |
01.06 |
O |
|
15 |
Public Participation & Awareness Programme |
PP |
10.80 |
13/10/2004 |
100 |
05.85 |
00.00 |
05.85 |
C |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
5221.78 |
8085.16 |
106.74 |
8191.90 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
# --> REFERS TO REVISED COST AND
REVISED DATE |
|
|
* --> REFERS TO SCHEMES NOT YET
APPROVED |
|
|
C --> COMPLETED, O-->
ONGOING, D--> DROPPED |
|
|
AFF-->
AFFORESTATION, BW--> BOUNDRY
WALL, LCS--> LOW COST SANITATION |
|
|
PID--> PART OF
I&D, CRE--> ELECTRIC CREMATORIA |
|
|
RM--> RISING
MAIN, I&D--> INTERCEPTION &
DIVERSION, LA--> LAND ACQUISTION |
|
|
PP--> PUBLIC
PARTICIPATION, OTH--> OTHER(MISCELLANEOUS
WORK), MPS--> MAIN PUMPING STATION |
|
|
RFD--> RIVER FRONT
DEVELOPMENT, STP--> SEWAGE TREATMENT
PLANT, P-S--> PART OF STP |
|
|
IPS--> INTERMEDIATE PUMPING
STATION, IWC--> IMPROVED WOOD
CREMATORIA, SWM--> COMPOST YARD |
|
|
PLC--> PART OF LCS |