SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                                [Rupees in Lakhs]

 

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











OTHER RIVER CONSERVATION PLAN

CITY : JALLUNDHAR

1

Sewage Treatment Plant

STP

2283.64

06/05/2002

100

2750.70

32.42

2783.12

C

2

Main Pumping Station at Garha

MPS

878.76

06/08/2001

100

890.22

-11.46

878.76

C

3

I&D (PART - I)

I&D

278.81

09/01/1996

100

278.70

00.00

278.70

C

4

I&D (PART-IV)

I&D

240.36

01/03/1996

100

236.02

00.00

236.02

C

5

I&D (PART-III)

I&D

193.10

10/01/1996

100

192.85

00.00

192.85

C

6

I&D (Part-II)

I&D

258.10

15/01/1996

100

257.99

00.00

257.99

C

7

I&D (Part-V)

I&D

274.82

25/01/1996

100

194.91

00.00

194.91

C

8

I&D (Part-VII)

I&D

131.77

14/10/1996

73

221.31

00.00

221.31

O

9

I&D (Part-VIII)

I&D

203.31

14/10/1996

94

263.97

82.00

345.97

O

10

I&D (Part-VI)

I&D

236.30

10/01/1996

90

177.61

03.78

181.39

O

11

Land Acquisition

LA

154.81

06/11/1995

100

2539.16

00.00

2539.16

C

12

Improved Wood Crematoria

IWC

06.43

21/01/1997

100

06.02

00.00

06.02

C

13

Low Cost Sanitation

LCS

68.87

17/01/1997

100

68.79

00.00

68.79

C

14

Afforestation/Plantation

AFF

01.90

07/06/1998

45

01.06

00.00

01.06

O

15

Public Participation & Awareness Programme

PP

10.80

13/10/2004

100

05.85

00.00

05.85

C











TOTAL

5221.78

8085.16

106.74

8191.90











 

 

 

      

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS