SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                                 [Rupees in Lakhs]

 

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











GOMATI ACTION PLAN

CITY : JAUNPUR

1

I&D(Part-I)

I&D

152.50

07/08/1995

100

153.31

00.00

153.31

C

2

I&D(Part-II)

I&D

150.00

12/02/1996

100

154.26

00.00

154.26

C

3

Low Cost Sanitation

LCS

16.35

09/08/1994

100

16.16

00.00

16.16

C

4

Land Acquisition

LA

54.21

03/05/1995

100

05.50

00.00

05.50

C

5

Improved Wood Crematoria

IWC

02.16

08/03/1995

100

02.42

00.00

02.42

C

6

Afforestation

AFF

01.95

07/04/1998

100

01.87

00.00

01.87

C











TOTAL

377.17

333.52

00.00

333.52











 

 

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS