SANCTION/PROGRESS OF SCHEMES UNDER NRCP                                                                                                                [Rupees in Lakhs]

 











S.NO.

SCHEME NAME

TYPE

SANC.COST
31/12/2009

SANC.DATE

%PHY PRG

EXP.TILL
MAR.09

EXP.DURING
2009-10

TOTAL  EXP
SEPT. 09

STATUS











GANGA ACTION PLAN - II(MAIN STEM)

CITY : KANPUR

1

Intermediate Pumping Station Munsi Punwa(P-III)

I&D

795.82

19/07/2001

91

808.34

00.00

808.34

O

2

Intermediate Pumping Station at RakhiMandi(P-IV)

I&D

938.26

19/07/2001

85

956.96

00.00

956.96

O

3

Reliving sewer for Bakermandi to Rakhimandi

I&D

589.92

21/03/2000

96

729.97

00.00

729.97

O

4

Relieving sewersfor Juhi, Transport Nagar & Govind

I&D

378.79

21/03/2000

100

537.70

00.00

537.70

C

5

Water Supply for South city Distt.

OTH

1061.05

10/08/1999

100

1641.93

00.00

1641.93

C

6

Solid Waste Management (Part-I)

SWM

198.70

08/02/1999

100

196.61

00.00

196.61

C

7

Water Supply Rehabilitation Works

I&D

129.60

15/07/1999

100

139.73

00.00

139.73

C

8

Diverting the waste water reaching to Bhaironghat

I&D

49.89

20/05/1997

100

36.28

00.00

36.28

C

9

Low Cost Sanitation

LCS

283.30

10/05/1998

100

255.60

00.00

255.60

C

10

Renovation of Existing Sewers & P.S.(Part-I)

I&D

274.08

19/07/1999

100

329.32

00.00

329.32

C

11

Renovation of Existing Sewers(Part-II)

I&D

277.12

02/07/1999

100

337.31

00.00

337.31

C

12

Main Pumping Station and Campus Development

MPS

1858.40

04/01/2005

20

924.42

164.77

1089.19

O

13

Solid Waste Management (Part-II)

SWM

286.06

08/08/2003

100

200.00

00.00

200.00

C

14

Tapping of Ganda Nala & Halwa Khanda Nala and dive

I&D

1050.27

16/02/2004

95

1055.02

00.00

1055.02

O

15

Common Chrome Recovery Plan (0.07 mld)

STP

105.27

28/06/2004

100

105.27

00.00

105.27

C











TOTAL

8276.53

8254.46

164.77

8419.23











 

 

           

# --> REFERS TO REVISED COST AND REVISED DATE

* --> REFERS TO SCHEMES NOT YET APPROVED

C --> COMPLETED, O--> ONGOING, D--> DROPPED

AFF--> AFFORESTATION,    BW--> BOUNDRY WALL,    LCS--> LOW COST SANITATION

PID--> PART OF I&D,    CRE--> ELECTRIC CREMATORIA

RM--> RISING MAIN,    I&D--> INTERCEPTION & DIVERSION,     LA--> LAND ACQUISTION

PP--> PUBLIC PARTICIPATION,    OTH--> OTHER(MISCELLANEOUS WORK),    MPS--> MAIN PUMPING STATION

RFD--> RIVER FRONT DEVELOPMENT,    STP--> SEWAGE TREATMENT PLANT,    P-S--> PART OF STP

IPS--> INTERMEDIATE PUMPING STATION,    IWC--> IMPROVED WOOD CREMATORIA,    SWM--> COMPOST YARD

PLC--> PART OF LCS