CHAPTER-II C-2
REVIEW OF OVERALL PERFORMANCE DURING
1998-99
1.0. FORESTRY AND WILDLIFE
1.1. INDIRA GANDHI NATIONAL FORESTRY ACADEMY (IGNFA), DEHRADUN
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Expdt. |
Physical Targets |
Physical Achievements |
|
IGNFA |
1.70 |
1.83 |
c) Compulsory Courses |
39 IFS Probationers of 1996-99 batch undergoing training. 55 IFS Probationers of 1997-2000 batch undergoing training. 2 Induction Courses for SFS officers promoted to IFS were conducted.
2 Compulsory Courses were conducted for 1 week & 2 weeks duration |
1.2. STATE FOREST SERVICE AND RANGERS COLLEGES
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Expedt |
Physical Targets |
Physical Achievements |
Reasons for shortfall, if any. |
|
SFS and Rangers Colleges. |
1.20 |
0.41 |
Training of SFS Officers in 3 colleges - 6 courses.
Thematic courses on Biodiversity Conservation & Participatory Forest Management for In-service SFS Officers with 25 participants – 2 courses.
Refresher Courses for in-service SFS Officers with 35 participants each – 7 courses.
Courses on Computer Application in Forestry for in-service SFS Officers with 35 participants each – 6 courses
Other courses - 3
|
3 courses
1 course
3 courses
3 courses
2 courses |
Due to inadequate demand for State Governments.
--
--
--
-- |
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Release |
Physical Targets |
Physical Achievements |
|
IIFM |
2.60
|
1.95
|
|
|
|
MDP/ Courses and Seminars: PGDFM/ MRM |
|
|
20 courses.
1 batch 1 batch |
20 courses
1 batch 1 batch. |
1.4. INDIAN PLYWOOD INDUSTRIES RESEARCH AND TRAINING INSTITUTE (IPIRITI), BANGALORE.
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Release
|
Physical Target |
Physical Achievements |
|
IPIRITI |
0.66 |
0.47 |
i) Inputs to improve capability in laboratory |
Continuing project.
|
|
|
|
|
ii) Training centre for mechanical wood industries |
Continuing project. |
|
|
|
|
iii) Establishment of Particle Board and Finger Jointed Lumber Unit. |
Not set up. |
1.5. INDIAN COUNCIL OF FORESTRY RESEARCH AND EDUCTION (ICFRE), DEHRADUN
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Release |
Physical Targets/Achievements |
|
ICFRE 1. Research (Plan) a) General component.
b) Externally Aided Component.
2. Education & Training.
|
30.00
34.21
1.80
|
15.00
11.00
0.60
|
* |
Formulation of state forestry research plans.
5 courses in ‘Research Methodology with emphasis on statistic’ for 100 scientists.
Requisite scientific journals procured.
Quarterly timber trade bulletin published.
Publication of Annual Report of ICFRE 96-97, IFLIN Newsletter, 11 brochures, 11 pamphlets etc. 3 films completed and 4 more films taken up Consultancy for development of HRD plan for ICFRE granted.
Studies on Genetic improvement of Pinus roxburghi, evaluation of natural resistance in 300 different clones/hybrids of populous deltoids against important defoliators in FRI, Dehradun
Studies on rare, endangered and medicinal plants carried out in FRI, Dehradun.
Computerisation of herbarium in FRI, Dehradun.
Institute of Forest Genetic and Tree Breeding, Coimbatore undertook studies in casuarina and eucalyptus.
Studies on seed production areas, collection of seeds, management and effecting cultivation on vegetation pattern undertaken in Institute of Rain & Deciduous Forest Research, Jorhat.
1.6.0. SURVEY AND UTILISATION OF FOREST RESOURCES
1.6.1. FOREST SURVEY OF INDIA (FSI)
(Rs. in Crores)
|
Name of the Activity
|
BE |
Actual expdt.
|
Physical Targets |
Physical Achievements |
|
FSI |
3.00
|
2.33 |
|
|
|
a) Forest Inventory (area in sq. km) |
|
|
25,000
|
55,794 |
|
b) Thematic Mapping (1:50,000 scale) |
|
|
260 map sheets. |
240 map sheets |
|
c) Vegetation Mapping (1:2,50,000) |
|
|
181 map sheets. |
183 map sheets |
|
d) Training (number of persons trained) |
|
|
90 |
135
|
|
e) Data Processing (area in sq.km) |
|
|
25,000 |
38,969
|
1.7. FOREST CONSERVATION
Under the Scheme, Strengthening of Forest Divisions, 7 Regional Offices are implementing the Forest (Conservation) Act and monitoring of Environmental Clearances accorded by the Ministry under Environment (Protection) Act. The physical and financial targets/achievements during 1997-98 are as under:
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Expenditure |
Physical Targets. |
Physical Achievements. |
|
Strengthening of Forest Division. |
3.25 |
3.02 |
a) Monitoring of Forest Conservation Projects approved under FCA, 1980. Target: 950 |
450 |
|
|
|
|
b) Monitoring of Environmental Projects approved under EPA, 1986. Target: 400. |
284 |
1.8. FOREST PROTECTION AND REGENERATION
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Release |
Physical Targets (in ha) |
Physical achievements (in ha) |
|
Association of Scheduled Tribe and Rural Poor in Regeneration of Degraded Forests. |
2.10 |
1.57 |
10,550 |
10,570 (During VIII- 8330 ha and in 1997-98 – 2240 ha.) |
1.9. MODERN FOREST FIRE CONTROL METHODS IN INDIA
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Expdt.
|
Physical Targets |
Physical Achievements |
|
CSS for Introduction of Modern Forest Fire Control Methods in India. |
2.70 |
0.61 |
11 States to be assisted. |
States assisted.* |
|
Central Component |
0.40 |
0.17 |
|
|
*Targets not fully achieved due to non-finalisation of EFC Memo.
1.10.0. WILDLIFE
1.10.1 NATIONAL ZOOLOGICAL PARK
(Rs. in Crores)
|
Name of the Activity |
B.E. |
Actual Expenditure |
Physical Targets |
Physical Achievements
|
|
Development work in NZP |
0.75 (Capital) 0.20 (Plan)
|
0.40 (Capital) 0.04 (Plan) |
Improvement of Chimpanzee, Chinkara Zebra, Black Swan enclosures etc. |
In progress. Some works have been completed. |
1.10.2. WILDLIFE INSTITUTE OF INDIA (WII)
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Expenditure |
Physical Targets (No. of persons)
|
Physical Achieve-ments (No. of persons) |
|
WII |
3.85 |
2.72 |
|
|
|
a) M.Sc. course in Wildlife Science. |
|
|
11 |
9 |
|
b) PG Dip. Course in Wildlife Management. |
|
|
30 |
20 |
|
c) Certificate Course in Wildlife Management |
|
|
30 |
17 |
|
d) Field Workshop/ Courses. |
|
|
120 |
96
|
1.10.3. STRENGTHENING OF WILDLIFE DIVISION AND CONSULTANCIES FOR SPECIAL TASKS
(Rs. in Crores)
|
Name of the Activity
|
BE |
Actual Expenditure |
Physical Targets
|
Physical Achievements |
|
Strengthening of Wildlife Division |
1.02 |
0.62
|
To provide funds for establishment, office expenses and travel for Regional Offices, Central Wildlife Division and Consultancies for Special Tasks. |
Achieved |
1.10.4. NATIONAL PARKS AND SANCTUARIES
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Expdt. |
Physical Targets |
Physical Achievements |
Reasons for shortfall, if any |
|
Development of National Parks and Sanctuaries. |
12.00 |
4.16 |
To provide assistance for 250 National Parks & Sanctuaries. |
Assistance was provided to State Govts./UTs for 135 National Parks and Sanctuaries. |
EFC approval fir the scheme with modifications for IX Plan has been obtained. CCEA approval is awaited.. |
1.10.5. CENTRAL ZOO AUTHORITY (CZA)
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Expenditure |
Physical Targets/ Achievement
|
|
CZA |
5.00 |
4.50
|
* |
*National Zoo Policy,1998 formulated. The scheme ‘Grants-in-aid to CZA’ was approved by EFC with some modifications. Approval of Finance Minister is awaited.
1.10.6. ANIMAL WELFARE BOARD OF INDIA (AWBI)
(Rs. in Crores)
|
Name of Activity. |
BE |
Actual Expdt. |
Physical Targets/Achievements |
|
AWBI |
4.23
|
2.75 |
* |
*Assistance has been released to 78 Animal Welfare Organisations .
9,917 operations on stray dogs as a part of ABC programme have been carried out. 149 Animal Welfare Training Programmes have been conducted. The scheme has since been transferred to Ministry of Social Justice and Empowerment.
1.10.7. PROJECT TIGER (PT)
Assistance of Rs.8.78 crores was given to 23 identified Tiger Reserve areas during 1998-99 upto October, 1998.
1.10.8. ECO-DEVELOPMENT IN AND AROUND PROTECTED AREAS
(Rs. in Crores)
|
Name of the Activity Physical Targets |
Physical Achievements |
Reasons for shortfall, if any. |
|||||
|
Eco-development around Protected Areas. |
8.00 |
4.05 |
To provide financial assistance to 80 National Parks and 18 Project Tiger areas.
|
Achieved. |
- |
||
|
India: Eco-development Project (World Bank aided Scheme). |
58.83 |
11.05 |
Release of funds to 7 Project States. |
Assistance was given to 7 Project States. |
CCEA’s approval accorded on 14/10/97. |
||
1.10.9. PROJECT ELEPHANT (PE)
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Release |
Physical Targets |
Physical Achievements |
Reasons for shortfall, if any. |
|
PE |
4.50 |
4.34 |
Elephant range states to be provided financial assistance. |
Achieved. |
1.11. NATIONAL AFFORESTATION & ECO-DEVELOPMENT BOARD
(Rs. in Crores)
|
Name |
B.E.
|
Actual Expenditure |
Physical Targets |
Physical achievement |
|
Integrated Afforestation and Eco-development Projects Scheme(IAEP)
Fuelwood/Fodder Projects Scheme (AOFFP)
Non-timber Forests Produce (including Medicinal Plants) scheme (NTFP)
Grants-in-aid scheme (for voluntary agencies)
Seed Development Scheme |
33.00
40.00
11.00
1.55
2.60 |
28.84
25.08
9.27
0.84
0.77 |
45,274 ha.
64,114 ha.
14,228ha.
--
-- |
Progress Report yet to be received
32000 ha.*
7917*
47 agencies assisted
-- |
The Scheme was launched during 1989-90 with an objective of rehabilitation of tribal families affected under relocation plan of Project Tiger areas. An amount of Rs. 3.00 crores was released to various State Governments under the Scheme.
1.13. BOTANICAL SURVEY OF INDIA (BSI)
The BSI is responsible for identification and conservation of genetic resources in the country.
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Expdt. |
Physical Targets |
Physical Achievements |
|
BSI
|
4.00
|
1.65
|
Exploration surveys 72 tours Collection of specimens Ca 14000.
Preservation of specimens Ca 12000
Coverage of species under threat in the publication of the Red Data Book – 42.
Publication.-5 |
37 tours Ca 8500 Ca 7000 20
5 |
1.14. ZOOLOGICAL SURVEY OF INDIA (ZSI)
The ZSI is responsible for the exploration and survey of faunal resources and research on Taxonomy, biology, ecology, wildlife, animal population and behaviour. Its achievements during the year are as under:
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Expdt. |
Physical Targets |
Physical Achievements |
|
ZSI
|
2.95
|
1.40
|
Exploration and survey – 64.
Status survey of endangered species – 2.
Taxonomic studies – Identification of collecting material.
Publication
Computerization of collected data - 800 data
Renovation of Indian Museum. Calcutta.
ENVIS on Bio-diversity (Fauna) computerization of available data |
41
1
Identification in progress.
Editing of 2 volumes in progress. Annual Report of ZSI for 1995-96. State fauna of Meghalaya – Vol.V-VIII CRC work completed.
Data entry work in progress.
Work at MBS and NNRS in progress.
Data entry in progress. |
(Rs. in Crores)
|
Name of the scheme |
BE |
Actual Expdt. |
Physical Targets |
Physical Achievements |
Reasons for shortfall, if any |
ii) Estt. Of Eco-clubs |
3.50
|
0.46 |
Different activities under the campaign to be completed
1200 |
The campaign is in advanced sage and would be completed in time.
1600 |
The expenditure is low as the major programme NEAC picks up during November/December
-- |
Workshops |
0.30 |
0.08 |
65 |
57 |
Suitable proposals were not received |
1.16. ENVIRONMENTAL POLICY AND LAW
(Rs. in Crores)
|
Name of the Scheme |
B.E. |
Actual Expdt. |
Reasons for shortfall, if any |
|
0.25
|
0.08 |
Due to restructuring of activities, this could not be utilised upto the target.
|
|
1.50 |
-- |
Act could not be put into operation
|
Physical Target:
Physical Achievement:
1.17. WORLD BANK AIDED INDUSTRIAL POLLUTION CONTROL PROJECT
(Rs. in Crores)
|
Name of the activity |
B.E.
|
Actual Expdt.
|
Reasons for shortfall, if any |
Prevention Project. |
33.00 |
28.30 |
Additional Provision of Rs.11 crores has sanctioned anticipating that the expenditure will go beyond BE.
Process of procurement of equipment have expedited will NTPC + CPCB for early procurement of equipment. |
|
7.16 |
1.10 |
Negotiation of the project could not be finalized |
Physical Target:
1. World Bank aided Industrial Prevention Control Project
a) Industrial Pollution Control Project
- Procurement of equipment for 4 SPCBs.
- Construction of Labs for 4 SPCBs.
- Training for SPCB personnel.
- Construction of CETPs.
- Awarded for Demo Projects.
- Award of projects under TA components.
b) Industrial Pollution Prevention Project
Award of ToRs 4,7 & 8 release of 1st instalment for ToRs 4,7 & 8 and release of 2nd instalment ToRs 1A, B,2,3,5 & 6
Project is due for negotiation
Physical Achievements:
1. World Bank aided Industrial Prevention Control Project
a) Industrial Pollution Control Project
b) Industrial Pollution Prevention Project
2. World Bank aided Hazardous Substance Management Project
1.18.NATIONAL MUSEUM OF NATIONAL HISTORY
(Rs. in Crores)
|
Name of the scheme |
B.E. |
Actual Expenditure |
Physical Targets/ Achievements |
Reasons for shortfall, if any |
|
National Museum of Natural History |
2.50 |
1.31 |
* |
-- |
*Collection of specimens for RMNH and NMNH was partially achieved.
IInd Phase of construction of building of RMNH, Bhopal is in progress.
Ist Phase of building of RMNH, Bhubaneshwar is ready for possession.
300 teachers trained trained at NMNH and 150 teachers at RMNH, Mysore for formal teaching programme.
Training of staff in computer operation for Bio-Science Computer facility has been achieved.
A large number of educational programmes, outreach activities were conducted for school children, college students, teachers, family groups, handicapped children and rural public.
Development of second gallery at RMNH, Mysore – exhibits developed.
1.19. ENVIRONMENTAL IMPACT ASSESSMENT
(Rs. in Crores)
|
Name of the Scheme |
BE |
Actual Expdt. |
Physical Target/Achievements |
Reasons for shortfall, if any |
|
Environmental Impact Assessment |
1.60 |
1.05 |
The objective of Impact Assessment division is to assess the Impact of any development Projects from Environment angle which is referred to this Ministry. Therefore there is no physical target and achievement. |
-- |
1.20. CIVIL CONSTRUCTION UNIT
(Rs. in Crores)
|
Name of the Activity |
BE/RE |
Actual Expdt. |
Physical Targets (No. of works) |
Achievements (No. of works) |
Reasons for shortfalls if any Under PE Sanction Progress awaited |
|
|
Forestry & Wild Life |
3.25 |
0.55 |
28 |
- |
16 |
12 |
|
Ecology & Wild Life |
6.15 |
2.76 |
51 |
1 |
31 |
19 |
|
Environment Education/Training/Extention |
2.50 |
0.45 |
4 |
1 |
3 |
- |
|
Civil Works |
1.40 |
1.00 |
-- |
-- |
-- |
-- |
|
Grand Total |
13.30 |
4.76 |
83 |
2 |
50 |
31 |
1.21. ENVIRONMENTAL INFORMATION SYSTED (ENVIS)
(Rs. in Crores)
|
Name of the scheme |
BE Plan Non Plan |
Actual Expenditure Plan Non Plan |
Physical Targets/ Achievements |
|
ENVIS |
1.50 0.30 |
1.42 0.14 |
* |
*Physical Target and Achievements:
1.22. CENTRES OF EXCELLENCE
(Rs. in Crores)
|
Name of the scheme |
BE
|
Expdt.
|
Physical Target and Achievements |
|
CENTRES OF EXCELLENCE |
3.50 |
2.70 |
All the Centres continued their activities in their respective fields and special activities like organisation of seminars/Exhibitions etc. were undertaken. |
1.23. NATIONAL NATURAL RESOURCES MANAGEMENT SYSTEMS (NNRMS)
(Rs. in Crores)
|
Name of the scheme |
BE Plan |
Actual Expdt. Non Plan |
Physical Targets/Achievements
|
|
NNRMS |
1.00 |
0.91 |
* |
Physical Target & Achievements:
1.24. PARYAVARAN VAHINI
(Rs. in Crores)
|
Name of the scheme |
BE
|
Actual Expdt.
|
Physical Targets/Achievements
|
|
Paryavaran Vahini |
0.50 |
0.18 |
Proposal for setting up new Paryavaran Vahinis in the identified districts have been processed. |
Reasons for shortfall:
Financial assistance to the existing vahinis could not be released due to non submission of requisite financial documents by the concerned State Governments. Efforts are being made to get the documents from the State Governments at the earliest possible.
1.25. NATIONAL RIVER CONSERVATION DIRECTORATE
(Rs. in Crores)
|
Name of the activity |
BE
|
Actual Expend. |
Physical Target |
Physical Achievement |
Reasons for shortfall, if any
|
|
1. GAP-I
2. GAP II a. YAP b. GoAP c. DAP d. GAP II MS e. GAP II SC f. CETP
3. NRAP
TOTAL |
12.70
165.00
14.00
191.70 |
3.28
68.75 0.00 0.00 9.00 1.50
14.00
96.53 |
Completion of remaining 7 schemes To monitor progress/completion of schemes " " "
"
|
--
24 schemes completed 8 schemes completed.
18 schemes completed
50 Schemes |
The shortfall in expenditure in 1998-99 was mainly on account of slow progress made in the implementation of the River Action Plans owing to reluctance of the State Governments to provide their matching share of funds. The issue has been resolved, after the decision of the CCEA to permit 100% funding by the Government of India. |
GAP(Ganga Action Plan); YAP (Yamuna Action Plan); GoAP (Gamti Action Plan); MS (Main Stem); SC (Supreme Court); CETP (Common Effluent Treatment Plant).
1.26. ASSISTANCE FOR ABATEMENT OF POLLUTION
(Rs. in Crores)
|
Name of the scheme |
BE
|
Expenditure
|
Reasons for shortfall, if any |
|
Assistance For Abatement of Pollution |
1.00 |
0.40 |
Shortfall is due to non-receipt of demands from various SPCBs/UT PCCs. However, earmarked amount can be utilised well within the current financial year. No physical targets were set |
1.27. REIMBURSEMENT OF WATER CESS
(Rs. in Crores)
|
Name of the scheme |
BE |
Expdt. |
Targets and Achievements |
|
Reimbursement of Water Cess (Non-Plan) |
50.00
|
12.62
|
Shortfall is due to non-receipt of Cess deposits from various SPCBs/UT PCCs. |
1.28. TAJ PROTECTION MISSION
(Rs. in Crores)
|
Name of the scheme |
BE
|
Expdt. |
Physical Targets/ Achievements |
Reasons for shortfall |
|
TAJ PROTECTION MISSION |
50.00 |
--
|
* |
The concept paper on the Taj Protection Mission has been sent after seven months by the Government of Uttar Pradesh. As a result of which delay has been occurred for the approval of EFC and finalisation of the CCEA note. |
*Physical Target
*Physical Achievements
Rs. in Crores)
|
Name of the Activity |
BE Plan NonPlan |
Actual Expdt. Plan Non Plan |
Physical Target/ Achievements |
|
CENTRAL POLUTION CONTROL BOARD |
8.00 6.73 |
3.11 3.46 |
* |
During the current Annual Plan (1998-99), the important activities which have been taken up are;
(Rs. in Crores)
|
Name of the activity |
BE
|
Actual Expdt. |
Physical Target/ Physical Achievements |
|
Environmental Audit
Environmental Statistics and Mapping
Adoption of Clean Technologies in Small Scale Industries |
0.10
0.10
0.10 |
0.10
0.10
0.10 |
Training programmes on Environmental Audit in the sectors of pulp and paper, cement, distilleries and fertiliser have been sponsored during the year. Environmental Audit update has also been brought out during the year. Preparation of sector specific manual for fertiliser industry has also been sponsored during the year. Preparation of Environmental Atlas for various districts. A project Integrated Coastal Environmental Management Plan in the region between Visakhapatnam and Kakinada has been sponsored to EPTRI, Hyedrabad.
Training and awareness programmes in selected sectors of small scale industry. Waste minimisation demonstration studies in selected sectors of SSI. Training and awareness programmes and short duration education wrokshops for small scale industry sector and for entrepreneurs in selected sectors are being conducted by DC:SSI. Studies on waste minimisation and demonstration in Chemical Sector and Bulk drug industry have been sponsored. |
1.31. CLEAN TECHNOLOGY
(Rs. in Crores)
|
Name of the Activity |
BE
|
Actual Expdt.
|
Physical Target |
Physical Achievements |
Reasons for shortfall, if any |
|
1. Sustainable Development Strategies
2. Development & promotion of clean technology |
5.5
-- |
1.17
-- |
Two Carrying Capacity Studies to be completed.
Approval awaited to set up ICPC |
Two Studies under completion
-- |
--
-- |
1.32. BIODIVERSITY CONSERVATION
The draft National Strategy and Action Policy for Biodiversity has been revised, and was submitted to the Committee of Secretaries for approval. As suggested by the Cabinet Secretariat, the draft has been abridged and resubmitted to the Committee of Secretaries. A draft Cabinet note alongwith the draft outline of bio-diversity legislation was circulated to concerned Ministries/Departments for their comments. Comments received were analyzed and the draft revised. A meeting of small group of experts to discuss the revised draft was held on 27.10.98 under the chairmanship of Minister for Environment and Forests.
1.33. ASSISTANCE TO BOTANIC GARDENS:
This Scheme is aimed at conservation and propagation of plant and genetic resources. Its
achievements in the year are given below:-
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Expdt. |
Physical Targets |
Physical Achievements |
|
Assistance to Botanic Gardens |
0.52 |
0.52 |
Inviting proposals from existing Botanical Gardens. . |
Botanic gardens were provided financial support. |
1.34. RESEARCH AND ECOLOGICAL REGENERATION
(Rs. in Crores)
|
Name of the activity
|
BE
|
Actual Expdt. |
Physical Targets/ achievements |
|
Research & Development
|
4.00 |
1.98 |
* |
*Physical targets/achievements
During 1998-99, more than 112 projects continued to progress under the Environmental Research Programme, Man & Biosphere Programme & the Research programme for the Eastern & Western Ghats. Up to December 1998, 33 new projects have been sanctioned. Twenty more new projects are expected to be initiated by March, 1999. Forty eight projects were reviewed during 1998-99 through Expert Committees in all three programmes.
The B.P. Pal National Environment Fellowship Award for Biodiversity for the year 1998 was awarded to Dr. Shashi Kant, Department of Biosciences, University of Jammu, Jammu. The Pitamber Pant National Environment Fellowship Award for 1998 was given to Dr. U.C. Mishra, Director, Health, Safety & Environment Group, BARC, Mumbai.
1.35. G.B. PANT INSTITUTE OF HIMALAYAN ENVIRONMENT & DEVELOPMENT
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Expdt. |
Physical Targets |
Physical Achievements |
Reasons for shortfall, if any. |
|
GB Pant Institute of Himalayan Environment & Development. |
4.78 |
2.03 |
Strengthening of on-going R&D Projects to be carried out. Buildings of Kullu unit to be completed and Sikkim unit to be expedited. |
All R&D targets were achieved. Kullu unit construction nearly completed . Sikkim unit work of construction started. |
Work area restricted and new project initiation delayed due to insufficient manpower & funds. |
1.36. INTEGRATED ACTIOIN ORIENTED R&D AND EXTENSION PROJECTS IN HIMALAYAN REGION
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Expdt. |
Physical Targets |
Physical Achievements |
|
Integrated Action Oriented Eco-development |
0.40 |
0.10 |
Continuation of ongoing projects and new projects.
|
Satisfactory. |
1.37. HAZARDOUS SUBSTANCES MANAGEMENT
(Rs. in Crores)
|
Name of the scheme |
BE |
Actual Expdt. |
Target/achievements |
|
Hazardous Substances Management |
2 |
0.35 |
* |
* Targets and Achievements
Hazardous Waste Management:
Court Cases:
1.38. CONSERVATION AND MANAGEMENT OF MANGROVES
The Scheme aims at conservation and management of identified mangroves. Its achievements during the year are as follows:
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Expdt. |
Physical Targets |
Physical Achievements |
Reasons for shortfall, if any |
|
Conservation and Management of Mangroves and Coral Reefs. |
1.56 |
0.51 |
MAPs for 6 mangroves and 2 coral reefs. |
MAPs for 4 mangroves. |
Fresh approval of the scheme awaited. |
1.39. BIOSPHERE RESERVE
The Scheme is intended to conserve representative ecosystems. Its achievements during the year are as follows:
(Rs. in Crores)
|
Name of the Activity |
BE |
Actual Expdt. |
Physical Targets |
Physical Achievements |
Reasons for shortfall, if any. |
|
Biosphere Reserve. |
2.62 |
0.99
|
Convening of meeting of National Committee for approval of MAP in respect of Biosphere Reserves. Evaluation of MAP and research activities. |
Meeting of National Committee and Research Advisory Committee held. Evaluation proposed in January,1999. |
Not applicable. |
1.40. INTERNATIONAL COOPERATION
(Rs. in Crores)
|
Name of the scheme |
BE
|
Actual Expdt. |
Reasons for shortfall, if any |
|
Environmental Management Capacity Building Technical Assistance Projects |
36.00 |
6.67 |
Three components, of the project have been dropped |
|
India Canada Environmental Facilities |
1.00 |
-- |
No commodity will be donated by Canada |
|
Delhi, Surat Urban Environmental Project |
2.00 |
-- |
PIP for the Institutional strengthening of Gujarat Component has not been approved by World Bank |
|
International Cooperation activities |
1.25 |
0.51 |
Shortlisting of consultants are yet to be finalised |
Achievements: